Roof Restoration · Christ Church Oak Brook

Project Timeline

July 6 — August 28, 2026. Drag the timeline, click a step, or pick a date to see what will be on site that day.

Aerial view of Christ Church Oak Brook.
Step 1 of 9 Existing view Today
Color key
  • Crane
  • Scaffolding
  • Dumpster
  • Materials & forklift path
Current step Existing view
    Today

    Existing view

    The roof today. No work has started.

      Partners

      Project Team

      Trusted partners volunteering material, equipment, and labor.

      Notes

      What to expect

      Material staging

      Material is staged in the dedicated parking lot. From there it is moved to the flat roof. A boom truck is brought out only to lift material.

      Stained glass

      Plywood protects the stained glass during work. It comes off for services. The stained glass stays usable for Sundays.

      Phase 2 inspection

      The roof deck is inspected section by section. Any deck repairs are done before new cedar is installed on that section.

      Sunday access

      The sanctuary stays in use throughout the project. Scaffolding stays up around the sanctuary until the last section is finished.

      Total Investment $1,073,660

      All-in. This is the full cost of the project — scaffolding, crane, dumpster, material, labor, and cleanup.