Roof Restoration · Christ Church Oak Brook

Project Timeline

July 6 — August 28, 2026. Drag the timeline, click a step, or pick a date to see what will be on site that day.

Aerial view of Christ Church Oak Brook.
Step 1 of 9 Existing view Today
Color key
  • Crane
  • Scaffolding
  • Dumpster
  • Materials & forklift path
Current step Existing view
    Today

    Existing view

    The roof today. No work has started.

      Partners

      Project Team

      Trusted partners volunteering material, equipment, and labor.

      Materials

      What is going on the roof

      The same two materials are used across the steeple and the full sanctuary, so the entire roof reads as one piece from the ground.

      Natural Cedar Brava shake

      A composite cedar shake with the look and grain of natural cedar. Class A fire rated, freeze/thaw stable, and warrantied for 50 years. Goes on every section of the steeple and sanctuary roof.

      Profile
      Natural cedar shake
      Fire rating
      Class A
      Warranty
      50 year, manufacturer

      Kynar steel — burnished slate

      All drip edge, valleys, and flashings are 26-gauge Kynar-coated steel, color-matched to burnished slate. Kynar is the same finish used on modern architectural metal roofs and resists fading, chalking, and staining for decades.

      Use
      Drip edge, valleys, flashings
      Gauge
      26-gauge steel
      Finish
      Kynar, burnished slate
      Notes

      What to expect

      Material staging

      Material is staged in the dedicated parking lot. From there it is moved to the flat roof. A boom truck is brought out only to lift material.

      Stained glass

      Plywood protects the stained glass during work. It comes off for services. The stained glass stays usable for Sundays.

      Phase 2 inspection

      The roof deck is inspected section by section. Any deck repairs are done before new cedar is installed on that section.

      Sunday access

      The sanctuary stays in use throughout the project. Scaffolding stays up around the sanctuary until the last section is finished.

      Documents

      Paperwork & credentials

      Each link opens the source document.

      Total Investment $1,073,660

      All-in. Scaffolding, crane, dumpster, material, labor, and cleanup.

      • Landscape repair Locke & Ladder includes a $5,000 allocation toward landscape repair, applied after construction completes.
      • Permits Locke & Ladder pulls all required permits and invoices the church separately at cost.