Existing view
The roof today. No work has started.
Enter the street number to view the restoration timeline.
For board members and project staff only.
July 6 — August 28, 2026. Drag the timeline, click a step, or pick a date to see what will be on site that day.
The roof today. No work has started.
Trusted partners volunteering material, equipment, and labor.
Material is staged in the dedicated parking lot. From there it is moved to the flat roof. A boom truck is brought out only to lift material.
Plywood protects the stained glass during work. It comes off for services. The stained glass stays usable for Sundays.
The roof deck is inspected section by section. Any deck repairs are done before new cedar is installed on that section.
The sanctuary stays in use throughout the project. Scaffolding stays up around the sanctuary until the last section is finished.
All-in. This is the full cost of the project — scaffolding, crane, dumpster, material, labor, and cleanup.